What this calculator does
Paver takeoffs fail in two places: the joint and the base. A 200 × 100 mm paver with a 3 mm joint does not cover exactly 0.02 m², because the joint and the cut edges take space, and the base and sand are ordered by volume rather than by the number of pavers. This calculator handles the geometry in metres, adds a waste allowance for cuts and breakage, and converts the sand and base volumes to tonnes using typical bulk densities. It is a material estimate, not an installation design. The base depth in particular depends on soil type, drainage, traffic, and frost, and a driveway needs a thicker, better-compacted base than a garden path.
How to use it
- Enter the length and width of the paved area in metres.
- Enter the actual paver length and width in millimetres.
- Set the joint width from the installation pattern; 3 mm is common for tight joints.
- Add a waste allowance for cuts, breakage, and future repairs.
- Set the bedding sand and compacted base depths for your project.
How it works
Example calculations
Example 1: 5 × 4 m patio, 200 × 100 mm pavers, 3 mm joints
The patio is 20.00 m² and the order area with 5% waste is 21.00 m². Each paver plus joint covers 0.0209 m², so 1,005 pavers are needed. The 30 mm sand bed is 0.63 m³, and the 100 mm base is 2.10 m³.
Example 2: 8 × 3.5 m walkway, 300 × 150 mm pavers, 4 mm joints
The area is 28.00 m² and the order area with 8% waste is 30.24 m². The larger paver needs 646 pieces. Sand is 0.91 m³ (1.5 t) and base is 3.02 m³ (5.4 t).
Example 3: 12 × 6 m patio, 200 × 200 mm pavers, 3 mm joints
A 72.00 m² area with 5% waste needs 1,835 square pavers. Sand is 2.27 m³ and base is 7.56 m³. Larger pavers reduce the joint count but can need more cuts at the edges.
What the result means
The paver count is driven by the unit area, not the nominal paver size. A 200 × 100 mm paver with a 3 mm joint is 203 × 103 mm of installed footprint, which is about 4.5% more area than the paver alone; that difference matters on a large patio. Waste covers cuts at the perimeter, breakage, and a few spares, but a diagonal or curved pattern can waste much more. The sand layer is a bedding course, not a structural base; the compacted base does the load-bearing work. The tonnage figures are for ordering, not for structural design. Confirm base depth and compaction with a local supplier or engineer, especially for driveways and frost-affected ground.
Common mistakes
- Using the paver's nominal area without adding the joint.
- Ordering the exact count with no waste for cuts and breakage.
- Confusing the bedding sand depth with the compacted base depth.
- Forgetting edge restraints, which keep the field from spreading.
- Skipping compaction or using the wrong base aggregate.
Assumptions and limits
- The paved area is rectangular and the paver layout is a simple running bond.
- Joint width is uniform and the pavers are rectangular.
- Sand and base depths are compacted thicknesses, not loose depths.
- Bulk densities are 1.6 t/m³ for sand and 1.8 t/m³ for base aggregate.
- Waste covers cuts and breakage but not a complex pattern or a second handling loss.
Frequently asked questions
How many pavers are in a square metre?
It depends on the paver and joint. A 200 × 100 mm paver with a 3 mm joint covers about 0.0209 m², so roughly 48 pavers per square metre. A 200 × 200 mm paver with the same joint covers about 0.0412 m², or roughly 24 per square metre.
How deep should the base be?
A garden path may need 75–100 mm of compacted base, a patio 100–150 mm, and a driveway more, depending on soil and traffic. Frost-prone ground needs a deeper frost-protected base. Local practice and the paver manufacturer's guide should govern.
How much sand do I need?
A 25–40 mm bedding layer is common. The calculator uses the order area, so the sand covers the waste allowance too. Do not use the sand layer to correct an uneven base.
What is the difference between sand and polymeric sand?
Bedding sand levels the pavers. Polymeric sand is swept into the joints and hardens to reduce erosion and weeds. They are different products with different quantities; this calculator estimates bedding sand only.
Why add waste?
Perimeter cuts, breakage, and future repairs consume extra pavers. Five to ten percent is common for a simple layout; diagonal, herringbone, and curved patterns need more.
Can I use this for a driveway?
The geometry is the same, but the base and compaction requirements are higher. A driveway needs a structurally adequate base and may need a concrete or asphalt edge restraint. Confirm the design for vehicle loads.
Sources
2026 update
How to use the professional output
This page is not just a formula box. The result is designed to be checked, compared, and taken away.
- Professional worksheet. The result includes the inputs used, the method and scope, and a one-variable sensitivity check for finance calculators.
- A/B scenarios. Save two input sets in the browser and compare the primary, secondary, and breakdown figures side by side.
- Print / PDF and CSV. Print a branded worksheet, or export the year-by-year table when the calculator produces one.
The formulas and assumptions above still govern the number. The worksheet makes the estimate auditable; it does not make it a lender quote, tax return, or personalized advice.