What this calculator does
Deck footings are small individually and easy to underestimate collectively. A single 30 cm hole at 90 cm deep holds about 0.064 m³ of concrete, which sounds trivial until nine of them need 0.60 m³ and 36 bags. The geometry is a cylinder, so the volume grows with the square of the diameter: going from a 25 cm to a 30 cm hole adds about 44% more concrete for the same depth. This page keeps the diameter and depth in centimetres, converts to metres internally, and shows both the volume and a bag count so you can compare a ready-mix delivery with a pallet of bags. The numbers are a material estimate; the footing size, bell, and depth are set by the deck design and the local building code.
How to use it
- Enter the number of deck footings or post locations.
- Enter the hole diameter in centimetres, measured across the excavated hole.
- Enter the hole depth in centimetres, measured below grade.
- Add a waste allowance for over-digging and spillage.
- Read the volume per footing, the total volume, and the bag equivalent.
How it works
Example calculations
Example 1: 9 footings, 30 cm diameter, 90 cm deep, 5% waste
One footing = π × 0.15² × 0.90 = 0.0636 m³. Nine footings = 0.573 m³, and 5% waste gives 0.601 m³. At 0.017 m³ per 60-lb bag that is 35.4 bags, rounded up to 36.
Example 2: 4 footings, 40 cm diameter, 120 cm deep
One footing = π × 0.20² × 1.20 = 0.1508 m³. Four footings = 0.603 m³, and 5% waste gives 0.633 m³, or 38 bags. Larger diameter and depth together more than double the volume per footing compared with Example 1.
Example 3: 6 footings, 25 cm diameter, 80 cm deep
One footing = π × 0.125² × 0.80 = 0.0393 m³. Six footings = 0.236 m³, and 5% waste gives 0.248 m³, or 15 bags. A narrower hole is the fastest way to cut concrete volume, but confirm the required bearing area first.
What the result means
The total volume is a purchase quantity for a cylindrical hole. Real holes are rarely perfect cylinders: they are wider at the top, crumbly in sandy soil, and sometimes belled at the base for frost resistance. Each of those adds concrete. A ready-mix supplier usually has a minimum delivery charge, so for a small deck a pallet of bags is often cheaper even though the unit cost is higher; for a large deck the reverse is true. The bag equivalent assumes 0.017 m³ per 60-lb bag, which is a typical yield for pre-mixed concrete. Check the bag label, because yields differ by product and by how much water is added. The footing diameter and depth themselves are structural decisions: a deck drawing or a prescriptive code table should set them, not this calculator.
Common mistakes
- Using the post size instead of the hole diameter.
- Measuring depth above grade rather than below grade.
- Ignoring the quadratic effect of diameter on volume.
- Forgetting that a belled or over-dug hole takes more concrete than the cylinder.
- Ordering bags without checking the actual yield printed on the bag.
Assumptions and limits
- Each footing is a straight cylinder with the entered diameter and depth.
- The hole is measured below grade and is not belled or undercut.
- The default yield is 0.017 m³ per 60-lb (27 kg) bag of pre-mixed concrete.
- Waste covers normal over-digging and spillage, not a collapsed hole.
- The entered footing count matches the deck's post and beam layout.
Frequently asked questions
How much concrete is in one deck footing?
For a 30 cm hole 90 cm deep, about 0.064 m³, which is roughly four 60-lb bags. The exact figure is π × radius² × depth; halving the diameter cuts the volume to a quarter, and doubling the depth doubles it.
How many 60-lb bags make a cubic metre?
At 0.017 m³ per bag, about 59 bags make 1 m³. That is why ready-mix becomes cheaper beyond a few tenths of a cubic metre, once the delivery minimum is met.
How deep should a deck footing be?
Depth depends on the frost line, the soil, and the deck load. In cold climates footings must extend below the local frost depth; in warm climates they still need enough depth for bearing and uplift. Check the local code or a deck drawing.
Do I need a bell at the bottom of the footing?
Some codes and soil conditions call for a wider base or bell to spread the load and resist frost uplift. A bell adds concrete that this cylinder formula does not include, so add it separately or use the larger diameter for the belled section.
Should I use ready-mix or bags?
Compare the total volume with the supplier's minimum delivery and the cost of bags. Bags suit small decks and remote sites; ready-mix suits larger pours and gives a more consistent mix. Either way, have the full volume ready before you start placing.
Why does the calculator round bags up?
Concrete is sold in whole bags, and running short mid-pour creates a cold joint. Rounding up also covers the small loss that comes with mixing and placing.
Sources
2026 update
How to use the professional output
This page is not just a formula box. The result is designed to be checked, compared, and taken away.
- Professional worksheet. The result includes the inputs used, the method and scope, and a one-variable sensitivity check for finance calculators.
- A/B scenarios. Save two input sets in the browser and compare the primary, secondary, and breakdown figures side by side.
- Print / PDF and CSV. Print a branded worksheet, or export the year-by-year table when the calculator produces one.
The formulas and assumptions above still govern the number. The worksheet makes the estimate auditable; it does not make it a lender quote, tax return, or personalized advice.