Formwork is the temporary edge that holds wet concrete in place until it cures. For a simple slab on grade it is usually the least expensive part of the pour, but running short of boards halfway through is a problem, and over-ordering leaves waste. This calculator estimates the edge formwork from the slab perimeter and thickness, then converts the contact area into boards using the board size you plan to use. It also reports the concrete volume so the formwork and the pour can be planned together. The count covers edge forms only. It does not include stakes, bracing, release agent, or formwork for beams, steps, openings, or a raised slab, and it assumes the boards can be cut and reused as planned.
How to use it
- Enter the slab length and width in metres.
- Enter the slab thickness in millimetres, including any haunch or thickened edge.
- Measure a board you plan to use: length in metres and height in millimetres.
- Choose a waste allowance for cutting and damaged edges.
- Check the board rows; a board shorter than the slab thickness needs more than one row.
- Use the concrete volume to order the pour and the boards together.
How it works
Example calculations
Example 1: A 10 × 6 m slab at 150 mm
The perimeter is 32.0 m and the contact area is 4.80 m². With 3.6 m × 200 mm boards, each covers 0.72 m², so 8 boards cover the edge with a 10% allowance. The slab contains 9.0 m³ of concrete.
Example 2: A thicker small slab
A 6 × 4 m slab at 250 mm has a 20 m perimeter and a 5.0 m² contact area. The 300 mm boards cover the full thickness in one row, and 7 boards are needed with 15% waste. The pour is 6.0 m³.
Example 3: A large slab with two board rows
A 20 × 10 m slab at 400 mm needs 2 rows of 200 mm boards, or 120 linear metres of formwork. At 0.84 m² per board, the order is 32 boards. The slab is 80 m³.
What the result means
The perimeter is fixed by the slab size, but the contact area grows with thickness. A 150 mm slab needs a single row of 200 mm boards; a 400 mm slab needs two rows of 200 mm boards, doubling the linear formwork and the board count. The waste allowance should reflect the number of cuts and the condition of the boards; reusing boards from a previous pour lowers the real cost but not the count if they are already cut short. The concrete volume is included as a cross-check: if the formwork count seems high relative to the pour, check the thickness and board height. The estimate does not include formwork for the slab edges that are not straight, and it assumes the boards are supported by stakes and bracing that are counted separately.
Common mistakes
- Using the slab area instead of the perimeter for edge formwork.
- Forgetting to round up the board rows when the board is shorter than the slab thickness.
- Ordering boards by area without allowing for cuts and damaged edges.
- Ignoring the formwork needed for steps, openings, or thickened edges.
- Forgetting stakes, bracing, and release agent in the material list.
- Treating the concrete volume as the formwork quantity or vice versa.
Assumptions and limits
- The slab is rectangular and the edge formwork runs around the full perimeter.
- The slab thickness is uniform around the edge.
- Boards are rectangular and can be cut to fit.
- The waste allowance covers cutting and minor damage, not major redesign.
- Stakes, bracing, release agent, and any interior formwork are excluded.
- The concrete volume is a geometric estimate, not an order quantity with overbreak.
Frequently asked questions
How many boards do I need for a slab edge?
It depends on the perimeter, thickness, and board size. A 10 × 6 m slab at 150 mm needs 8 boards of 3.6 m × 200 mm with 10% waste. Always round up.
Do I need formwork under a slab on grade?
A slab on grade usually needs edge formwork only, because the ground acts as the bottom form. A suspended slab needs full soffit formwork and temporary support, which is a different and much larger calculation.
Why does thickness affect the board count so much?
The formwork contact area is the perimeter multiplied by the thickness. Doubling the thickness doubles the contact area, and if the board height is fixed it can also double the number of rows. Both effects increase the board count.
Can I reuse formwork boards?
Yes, if they are cleaned, oiled, and undamaged. Reuse reduces the cost but not the initial count; the calculator gives the quantity for one pour. For repeated pours, track the reuse and order only what is missing.
Does the calculator include formwork for beams or steps?
No. Beams, steps, openings, and raised edges need additional formwork and often temporary support. Add those separately or use a specialist take-off.
Is the concrete volume exact?
It is a geometric volume from length × width × thickness. Real pours need an allowance for overbreak, uneven ground, and waste, and the supplier may have a minimum order. Add a small margin rather than ordering exactly the calculated volume.
Sources
2026 update
How to use the professional output
This page is not just a formula box. The result is designed to be checked, compared, and taken away.
- Professional worksheet. The result includes the inputs used, the method and scope, and a one-variable sensitivity check for finance calculators.
- A/B scenarios. Save two input sets in the browser and compare the primary, secondary, and breakdown figures side by side.
- Print / PDF and CSV. Print a branded worksheet, or export the year-by-year table when the calculator produces one.
The formulas and assumptions above still govern the number. The worksheet makes the estimate auditable; it does not make it a lender quote, tax return, or personalized advice.