What this calculator does
Concrete stairs are usually priced and ordered by volume, but the shape is awkward to measure: the side profile is a series of steps, not a rectangle. A practical estimate treats the solid stair as a right triangle running from the bottom of the first riser to the top of the last one. That triangle captures the concrete under the steps, which is what most simple poured stair runs use. It deliberately leaves out a suspended waist slab, landings, foundation, and reinforcement, because those add volume and cost that depend on the structural design. The result is the number you take to a ready-mix supplier for a first quote, and the number you check against the drawing before you pour.
How to use it
- Count the number of risers (steps) in the run.
- Enter the riser height in centimetres, typically 17–18 cm for residential stairs.
- Enter the tread depth (going) in centimetres, excluding any nosing.
- Enter the stair width in centimetres.
- Add a waste allowance for spillage and uneven subgrade, then read the volume in m³.
How it works
Example calculations
Example 1: 12 steps, 18 cm riser, 28 cm tread, 1.0 m wide
Rise = 12 × 0.18 = 2.16 m. Run = 12 × 0.28 = 3.36 m. Volume = 1.0 × 2.16 × 3.36 ÷ 2 = 3.63 m³. A 5% allowance gives 3.81 m³, so order about 3.9 m³ or the nearest supplier increment.
Example 2: 15 steps, 17 cm riser, 30 cm tread, 1.2 m wide
Rise = 2.55 m and run = 4.50 m. Volume = 1.2 × 2.55 × 4.50 ÷ 2 = 6.89 m³. With 5% waste the estimate is 7.23 m³. Taller and wider stairs grow volume quickly because both rise and run scale with the step count.
Example 3: 5 steps, 18 cm riser, 30 cm tread, 1.0 m wide
Rise = 0.90 m and run = 1.50 m. Volume = 1.0 × 0.90 × 1.50 ÷ 2 = 0.675 m³. With 5% waste the estimate is 0.71 m³, which is small enough that a site mix may be more practical than a ready-mix delivery.
What the result means
The triangular estimate is the concrete under a solid stepped profile. It is close to the poured volume for a stair that sits on fill or on the ground with a stepped underside, which is common for garden and basement steps. It understates a suspended stair with a flat soffit and a waist slab, because that stair has a constant thickness under the steps plus the steps themselves. It also excludes the landing, the footing, and any upstand or cheek wall. For a structural stair, the engineer's drawing governs: use this figure for budgeting, supplier conversations, and sanity-checking a quote, not for ordering the final load without the drawing.
Common mistakes
- Entering centimetres in the riser and metres in the width without converting.
- Counting treads when the run actually has one more riser than treads, or the reverse.
- Ignoring the waist slab on a suspended stair, which can add 30–50% to the volume.
- Forgetting landings, footings, and cheek walls in the total concrete order.
- Ordering exactly the calculated volume with no allowance for spillage and uneven excavation.
Assumptions and limits
- The stair is a straight run with a constant riser and tread.
- The concrete fills a solid triangular side profile under the steps.
- Riser height and tread depth are measured in centimetres and converted internally.
- The stair width is constant across the run.
- Reinforcement, landings, footings, and a suspended waist slab are excluded.
Frequently asked questions
Does the calculator include the waist slab?
No. It estimates the stepped solid profile only. A suspended stair with a flat underside and a waist slab needs additional volume, typically the run length × width × slab thickness, plus the steps. Ask your engineer for the structural volume.
How many risers does a staircase have?
Count the vertical steps from the lower floor to the upper floor. A run with 12 risers usually has 11 or 12 treads depending on whether the top landing acts as the final tread. Use the riser count for the rise and the tread count for the run if they differ.
What riser height should I use?
Residential stairs commonly use 17–18 cm risers with 28–30 cm treads. Local code sets maximum riser and minimum tread; check it before building. The calculator accepts anything from 10 to 25 cm so you can test a design.
Why is the volume a triangle rather than a set of boxes?
Stacking the step boxes and summing them gives width × riser × tread × n(n+1)/2, which is close to the triangle formula width × (n × riser) × (n × tread) ÷ 2. The triangle is simpler, slightly conservative for a solid stair, and matches how ready-mix is ordered.
How much waste should I add?
Five percent is a reasonable default for a formed stair on prepared ground. Add more if the subgrade is uneven, the forms are complex, or the pour is small enough that a partial wheelbarrow is wasted. Round up to your supplier's minimum increment.
Can I use this for a curved or L-shaped stair?
Not directly. Split the stair into straight flights, estimate each one, and add the landing volume. Curved and winder stairs need a drawing-based takeoff because the tread width and run vary across the flight.
Sources
2026 update
How to use the professional output
This page is not just a formula box. The result is designed to be checked, compared, and taken away.
- Professional worksheet. The result includes the inputs used, the method and scope, and a one-variable sensitivity check for finance calculators.
- A/B scenarios. Save two input sets in the browser and compare the primary, secondary, and breakdown figures side by side.
- Print / PDF and CSV. Print a branded worksheet, or export the year-by-year table when the calculator produces one.
The formulas and assumptions above still govern the number. The worksheet makes the estimate auditable; it does not make it a lender quote, tax return, or personalized advice.